Generally, the advisory on fertilizer application is given based on soil test values.
If the soil testing is not done so far, it is advised to collect the soil sample (block wise) and send it to Coffee Research Sub Stations.
Based on the soil test values, the quantities of fertilizer required to be applied block-wise will be given for the next 3 years.
Application of Sulphur during post monsoon time is very important as Sulphur plays a key role in flower bud initiation.
Robusta Coffee (700kg of clean coffee or 28 bags of dry cherry per acre)
During blossom or backing irrigation time: Fertilizer required(kg per acre) : Urea 46 kgs + DAP 50 kgs + MOP 50 kgs OR Urea 65 kgs: SSP 144 kgs: MOP 50 kgs
Pre-monsoon period (late May/early June): Fertilizer required(kg per acre) :Urea 65 kgs; Rock Phosphate 128 kgs; MOP 50 kgs
Post monsoon time (September): Fertilizer required(kg per acre) :115 kgs Factomphos (20:20:0:13) and 50 kgs MOP
Robusta Coffee (500kg of clean coffee or 20 bags of dry cherry per acre)
During blossom or backing irrigation time: Fertilizer required(kg per acre) : Urea 35 kgs: DAP 40 kgs: MOP 39 kgs OR Urea 51 kgs: SSP 115 kgs: MOP 39 kgs
Pre-monsoon period (late May/early June): Fertilizer required(kg per acre) : Urea 51kgs; Rock Phosphate 102kgs; MOP 39kgs
Post monsoon time (September month: Fertilizer required(kg per acre) : 92kgs Factomphos (20:20:0:13) and 39kgs MOP
Sulphar requirement is high during this time